Statistics for the sewage piping system in Taipei City

 
 
Statistics Update Date MAY-31-2021 Unit: (meter)
Type Planned length Completed length Length yet to be built Percentage completed
Main trunk

47,762

47,762.00

0

100%

Sub trunk

79,160

77,218

1,942

97.55%

Branch

905,000

830,156

75,844

91.73%